Wet area renovation sequencing
The usual order of trades in a Pakenham 3810 bathroom or laundry renovation.
Illustrative image, not a completed customer project.
A bathroom or laundry renovation brings together demolition, plumbing, electrical, carpentry, sheeting, waterproofing, tiling and fit-off. Each stage hides the one before it, so the order matters. This guide sets out a typical sequence and the hand-over points between trades, so you know who checks what before it is covered up.
Every project is different, and the businesses doing the work set the actual order. Use this as a starting point for questions. When you are ready, send your renovation enquiry and up to three independent local businesses can respond. This website is a referral service and does not manage renovations.
Why does the order matter so much?
In a wet area, most of the important work ends up hidden. Pipes go inside walls and floors. Waterproofing goes under tiles. Framing and noggins for fixtures go behind sheeting. If a stage is skipped, rushed or done out of order, fixing it later means removing everything that was built on top.
A clear sequence also sets responsibility. When one trade finishes and the next starts, someone should check that the earlier work is ready. Without that, each trade can assume the other checked.
A typical sequence
The table shows a common order for a bathroom renovation. Your project may combine or reorder some steps.
| Stage | Typical work | Hand-over check |
|---|---|---|
| 1. Planning | Layout, fixtures, tiles, permits if needed | Final plan and selections agreed |
| 2. Demolition | Remove fixtures, tiles, sheeting | Damage and hidden problems recorded |
| 3. Structure | Repair framing, floor, add noggins and niche framing | Framing ready for services |
| 4. Rough-in | Plumbing and electrical inside walls and floor | Pipes and wiring in correct positions |
| 5. Sheeting | Wall and floor sheeting suited to wet areas | Sheeting fixed and ready for preparation |
| 6. Falls and screed | Form slopes to floor wastes | Falls checked before waterproofing |
| 7. Waterproofing | Membrane system to the wet area | Completion documented, cured |
| 8. Tiling | Floor and wall tiles, grout, movement joints | Waterproofing protected during tiling |
| 9. Fit-off | Fixtures, tapware, vanity, screen, lights | Fixtures sealed without damaging membrane |
| 10. Handover | Final clean, documents, care instructions | Records provided to owner |
Planning before demolition
Decide the layout, fixture positions and tile selections before demolition starts. Changes later are expensive, because they affect plumbing, framing and waterproofing. Points to settle early:
- Shower position and size, and whether it has a hob, step-down or level entry.
- Floor waste type and position, such as a centre waste or a linear drain.
- Vanity, toilet and bath positions.
- Niche positions and sizes.
- Grab rails or future grab rail supports.
- Tile sizes, which affect falls and layout.
Our tile layout planning page explains how tile size and layout interact with falls and fixtures. Our tile selection guide covers choosing tiles.
Some renovations need a building permit or involve work that must be done by registered or licensed practitioners. Check with the Building and Plumbing Commission or a building surveyor before work starts if you are unsure.
Demolition and what it reveals
Demolition removes the old fixtures, tiles and usually the wall sheeting in the wet area. This is when hidden damage shows up. Water-damaged framing, rotted floor sheeting, termite damage or poor old repairs may need fixing before anything new goes in.
Ask the business doing demolition to photograph and describe anything unusual before continuing. In homes built or renovated before 1990, old sheeting and underlays may contain asbestos and need assessment before removal. Our tile removal and preparation page covers this stage.
Rough-in: plumbing and electrical
With walls open, the plumber positions pipes, wastes and tapware bodies, and the electrician runs wiring for lights, fans, heated towel rails and power. Check with the Building and Plumbing Commission and Energy Safe Victoria about who can do plumbing and electrical work, and ask each trade for its compliance certificate where one applies.
Positions set at rough-in are hard to change later. Check tap heights, shower rose position, vanity waste height and power point locations against your plan before the walls are sheeted.
Sheeting and preparation
Wall and floor sheeting suited to wet areas is fixed over the framing. Junctions, corners and edges are prepared so the waterproofing can be applied. Who does sheeting varies: it may be a carpenter, a plasterer, the waterproofer or the tiler.
Who checks the substrate before waterproofing?
This is one of the most important hand-over points. The waterproofer should confirm that the surface is suitable for its system before applying it. Ask who does this check and whether it is recorded.
Falls to the floor waste
Wet area floors usually slope toward the floor waste so water drains away. Falls are often formed with a screed before waterproofing, though some systems differ. The tiler, waterproofer or another trade may do this. Agree who is responsible, and check the falls before the membrane goes on, because correcting them after waterproofing means removing the membrane.
Waterproofing
Waterproofing of domestic wet areas is covered by AS 3740 and by Victorian building requirements. The BPC describes waterproofing as a distinct class of domestic building work. The waterproofer applies the system to the required areas and allows it to cure according to the product instructions.
Ask the waterproofer:
- Which product system will be used?
- Which areas will be treated?
- How long it needs to cure before tiling.
- What documents will be provided on completion.
- Whether a flood test or other check will be done.
Our wet area waterproofing page explains the system in more detail.
Protecting the membrane
A membrane can be damaged by foot traffic, dropped tools, or other trades drilling or fixing through it. Ask who is responsible for protecting it between waterproofing and tiling, and what happens if it is damaged. Any damage should be reported and repaired before tiling covers it.
Tiling
The tiler lays floor and wall tiles over the cured membrane, using adhesives compatible with the waterproofing system. Movement joints at internal corners and changes of plane are filled with flexible sealant rather than grout. Ask the tiler to confirm that its adhesive is compatible with the membrane product.
Our bathroom tiling page and laundry tiling page cover room-specific tiling questions.
Fit-off
After tiling, the plumber fits tapware, the toilet, the vanity and the shower fittings, and the electrician fits lights, fans and power outlets. Shower screens are usually fitted last. Anything drilled through tiles must be sealed properly so water does not reach behind them. Ask each trade how it seals fixings and penetrations.
Handover and records
At the end, collect:
- Waterproofing product details and completion records.
- Plumbing and electrical compliance certificates where applicable.
- Tile range, batch numbers and spare tiles.
- Grout and sealant colour details.
- Care and maintenance instructions.
- Contact details for each business.
Our tiling handover guide covers what to check and keep.
How long does a bathroom renovation take?
That depends on the scope, the trades’ availability, curing times and what demolition reveals. Waterproofing and some adhesives need set curing times before the next stage, and waiting for each trade to return adds days. Ask each business for an expected timeline with the main stages and waiting periods marked, and plan the household around it.
Changes during the job
Changes after work starts are common and often cost more than expected because of the sequence. Moving a niche after sheeting means removing sheeting. Changing the shower position after waterproofing means removing the membrane. If you want a change, ask the businesses involved what it affects before agreeing. Get the change and any extra cost in writing.
Keeping a renovation record
A simple record helps everyone and is useful later. Keep:
- The plan and selections, with any changes.
- Photos of each stage before it was covered.
- Each business’s quote, invoice and contact details.
- Waterproofing records and compliance certificates.
- Tile, grout and sealant details.
Laundries and powder rooms
Laundries and powder rooms follow a similar sequence on a smaller scale. A laundry with a floor waste is a wet area and needs waterproofing where required. Cabinetry is usually fitted after tiling, but the splashback height and benchtop position should be settled before tiling. In a powder room, the toilet and vanity positions are fixed at rough-in, so confirm them early. Our laundry tiling page covers laundry details.
Single-bathroom homes
If the home has only one bathroom, the renovation leaves the household without a shower and possibly a toilet. Options include a temporary toilet kept working for part of the job, staying with family, or hiring a portable facility. Ask the businesses which stages need the toilet removed and for how long.
One business or several?
Some businesses manage the whole renovation, while others handle only one stage. If several businesses are involved, someone has to coordinate them. That may be a builder, one of the trades, or you. Ask each business which stages it covers, and who checks each hand-over point.